Line 12 Extension to Observatorio Starts Station Construction
Construction of three stations on the Metro Line 12 extension began Nov. 20, with the Mixcoac to Observatorio stretch due in 2028. See what is being built.

Construction of the stations and ventilation shafts for the Metro Line 12 extension began on Nov. 20, according to Infobae. Crews from the city’s Secretariat of Works and Services (Sobse) and from Metro CDMX are building the structures for three new stations: Valentín Campa, Álvaro Obregón and Observatorio.
Andrés Lajous, who heads the Agency for Trains and Integrated Public Transport, said the Mixcoac to Observatorio stretch will be finished in 2028. Operation of the new section had previously been planned for 2029.
What is being built
The extension covers 4.6 kilometers of underground route and three stations, with an investment of 11,000 million pesos financed by the National Infrastructure Fund (Fondo Nacional de Infraestructura). It will link the boroughs of Álvaro Obregón and Miguel Hidalgo. Work began in 2015.
The tunnel toward Observatorio is complete. With it finished, work now concentrates on the stations, their pedestrian entrances and the shafts (lumbreras), which provide ventilation and let crews bring in electromechanical equipment for installing the tracks. Station construction and the electromechanical phase are the last two phases of the project.
As of July 21, 2026, Valentín Campa showed 28% progress on underground work and Álvaro Obregón 30%, with crews building secondary tunnels and platform walls at the latter.
Observatorio terminal and connections
The Observatorio terminal will have five tracks and two underground platforms. It is meant to connect Line 12 with Metro Line 1, the Mexico City-Toluca Interurban Train and the Western Bus Terminal (Terminal de Autobuses del Poniente).
A bidding call for civil and complementary works at Observatorio was published in September. Avenida Sur 122 will be affected because the train workshop area will be located there. That work is scheduled for December 2026, once the bid result is known.
Why the tunnel took so long
Lajous said ground conditions forced crews to slow excavation to avoid risks to the tunnel and to homes above. In some areas progress was only three meters a month. President Claudia Sheinbaum Pardo said there were periods when digging advanced about one centimeter a month. Part of the terrain in Álvaro Obregón was an open-pit mine later filled with rubble, garbage and other weak material.
Sheinbaum said the tunnel runs below, but that the borough has “many fills” of rubble and other materials.
What it means for the existing line
The current stretch between Mixcoac and Tláhuac needed maintenance to reduce accelerated corrugation wear on the rails, mostly on curves with a radius under 400 meters. According to Infobae, authorities wanted to keep that problem from repeating on the extension.
A recent video tour by the content creator SNT: Movilidad Urbana showed steel structures and supports going in at the transition tunnel that will join the new section to the existing line. Among the shafts, Ruiz Dael is cited for its civil works progress, and the La Venta track shaft shows the most advance after months with none.
What to watch
The result of the Observatorio bidding and the start of workshop works on Avenida Sur 122, planned for December 2026, are the next scheduled steps.
Source: Infobae